The Road Calendar Behind Asbury, South Franklin's Next Neighborhood

"For development to move forward infrastructure must be first," Adam Ballash of Boyle Investment Company told Franklin's Board of Mayor and Aldermen on April 28, as the Williamson Herald reported. The board approved the Harlin development at that meeting. Boyle now calls it Asbury.

The vote decided what will go on the farm below Winstead Hill. The road commitments Boyle made decide when anything changes there. If you're comparing homes along Columbia Avenue, Hillview Lane or Coleman Road this winter, the road schedule tells you more than the site plan does.

What the April vote settled

The site is 311 acres at 1247 Hillview Lane. The plan calls for 249 residences, 32,000 square feet of commercial space, an 80-key hotel and 6.5 miles of walking and biking trails. Over the past year the vote count shifted on each piece. The board approved the plan of services 6-2, annexation 5-3, the Planned District zoning 6-2 and the development plan 5-3.

The land's history ties it to neighborhoods buyers already tour. Boyle's Asbury site traces the tract to a land grant that Ezekiel Polk, grandfather of President James K. Polk, acquired in the 1820s. Tom Harlin started a dairy there in the 1960s and grew it from 30 Holsteins to more than 400 head, with tanker trucks hauling milk down Hillview Lane to Purity Dairy in Nashville. The Harlins also leased and farmed hundreds of acres where Polk Place and Dallas Downs subdivisions now stand, along with the ground under today's Target, Kroger and Chick-fil-A. The dairy stopped operating about 20 years ago. Asbury covers the last large piece of the farm.

Boyle calls Asbury a showcase for the Village Green design guideline Franklin adopted through Envision Franklin in 2024. When the plan first went to a joint workshop of the aldermen and planning commission, designer Greg Gamble said its scale would be modeled on Westhaven, Leiper's Fork and Berry Farms, according to the Williamson Herald. Boyle also built Berry Farms and McEwen Northside, so buyers can walk around two of the company's finished Williamson County projects.

Late 2026: Mack Hatcher at South Royal Oaks

The first work near the site is not on Boyle's land. At the April meeting, Alderman Jason Potts said TDOT would improve and widen Mack Hatcher Parkway at South Royal Oaks Boulevard in the fourth quarter of 2026. He said the City would widen South Royal Oaks where it turns onto Mack Hatcher. The board's Sept. 22 agenda included a change order on the City's construction contract for the South Royal Oaks Boulevard and Royal Oaks Court intersection. If you're house hunting over the holidays, plan on work zones at that interchange as part of the south Franklin drive.

2027 to 2029: Coleman Road and Henpeck Lane before the first homes

This step sets the order for everything after it. Ballash told the board that Boyle would finish the Coleman Road and Henpeck Lane improvements during Phase 1, which runs from 2027 to 2029, before its first homes go up. The Nashville Business Journal reported in September that Boyle plans to break ground in 2027 and expects the project to become "an icon for South Franklin."

Gamble described that road work at the first workshop, as the Williamson Herald reported. It includes a new right-of-way connecting the property to Coleman Road. Henpeck Lane would be realigned to the south so that it meets Columbia Pike and Coleman Road at a four-way intersection. At a later meeting with Hillview-area neighbors, Boyle said it would pay for the road work before Harlin construction. That work includes traffic signals at Columbia Avenue and Henpeck Lane and at Columbia Avenue and Coleman Road, according to the Williamson Herald.

If you're looking at a house near Coleman Road or Henpeck Lane, this means the first visible change from Asbury will be new pavement and signals, not houses. The signals are also what everyone already living nearby would use first.

Late 2027: Columbia Avenue goes out to bid

Columbia Avenue is the corridor most south Franklin buyers drive on every day, and it has its own schedule. The City's project would widen it to five lanes from Mack Hatcher Parkway to Downs Boulevard. TDOT approved the City's request to begin buying right-of-way on July 12, 2023. According to Potts, citing City staff at the April meeting, the construction bid is scheduled to go out in late 2027. The board's Sept. 22 agenda carried a $694,723 amendment for design services on the project.

On this calendar, the Columbia Avenue widening and Asbury's Phase 1 could overlap. Alderman Greg Caesar told the board he drives Columbia Avenue every day and sees how congested it is, as the Williamson Herald reported. For homes in Polk Place, Dallas Downs and the streets off the Columbia Avenue retail strip, the widening is the project to follow, because it covers the stretch residents drive to Downs Boulevard and downtown.

2029 to 2030: the intersection that opens Phase 2

The second commitment controls Asbury's later homes. Ballash said the Columbia Avenue and Mack Hatcher intersection work will be finished before Phase 2 begins, and Phase 2 runs from 2029 to 2030. A plan revision in March 2026 proposed extending Mack Hatcher Parkway to Chimeric Drive and adding a two-lane connector toward Hillview Lane with an eight-foot multi-use path. The developer said Hillview's historic tree tunnel would not be touched, according to the Williamson Herald.

The intersection plan was designed with the next state project in mind. At the first workshop, the Williamson Herald reported, Alderman Potts asked whether the new Mack Hatcher and Columbia intersection would be built to state standards so it could tie into a future widening of Mack Hatcher, and Gamble said it would.

2032: Southeast Mack Hatcher

The last item on the calendar is TDOT's. WKRN reported on May 14 that the Southeast Mack Hatcher project would widen the parkway from two lanes to four median-divided lanes between State Route 96 East and Columbia Avenue. It would add a 12-foot multiuse trail, and construction is expected to start in 2032. The station reported that an extra $15 million brought TDOT's commitment to $40 million.

That puts the biggest change to south Franklin's east-west route about two years after Asbury's Phase 2 window closes. Asbury's later residents and today's homeowners along that loop will both be waiting on the same project.

What the calendar tells you about a south Franklin address

Asbury's mix of homes will put new kinds of housing next to the existing neighborhoods. Boyle plans a walkable hamlet with single-family homes in the style of downtown Franklin, brownstones and condominium flats with elevator access. Two- to eight-acre lots will surround the hamlet, next to the neighboring farms and estates, and more than 200 acres will stay as open space. Boyle presents the attached homes as the "Missing Middle" housing it says Franklin residents have asked for. On Boyle's schedule, those condo flats and brownstones arrive no earlier than the 2027 to 2030 phases.

Next door, a separate 79.89-acre Ingram tract was annexed into Franklin this spring with agricultural zoning. It is a reminder that not every annexed acre along this edge of town comes with a development plan.

If you're comparing south Franklin homes now, put the address on this calendar:

  • Near Hillview Lane, Coleman Road and Henpeck Lane, the road improvements come first, from 2027 to 2029.
  • On the Columbia Avenue corridor, the widening bid follows in late 2027.
  • At Columbia and Mack Hatcher, the intersection is due before 2029.
  • The full Southeast Mack Hatcher widening is set to start in 2032.

A house that looks out on an open field this year may look out on a new signal by 2029. A house on a road scheduled for widening has a known start date. Neither is a reason to rule out a street.

Frequently asked questions

Where exactly is Asbury? It is on the 311-acre Harlin farm at 1247 Hillview Lane, below Winstead Hill at the south edge of Franklin's city limits, where Polk Creek runs through a grassy basin.

When does construction begin? The Nashville Business Journal reported that Boyle plans to break ground in 2027. Boyle has said the Coleman Road and Henpeck Lane work comes before its first homes.

Who else has a stake in the roads around it? TDOT, the City of Franklin and Boyle each have their own pieces. TDOT has the Mack Hatcher projects, the City has Columbia Avenue and South Royal Oaks, and Boyle is paying for the Coleman and Henpeck work.

If you own a home in south Franklin and want to know how this road calendar affects your timing, The Bickerstaff Group is glad to go through it with you, street by street. Start with a free home valuation, and we'll talk about where your address sits on the 2026 to 2032 schedule. If you're still choosing between parts of town, our Franklin neighborhood guide is a good place to start.

Work With Us

Our expansive network and white-glove service ensure a bespoke experience for both buyers and sellers.
Contact Us
Follow Us